|
Project Summary for
Don Pedro Reservoir Hydrocarbon Contamination
Owner: Turlock Irrigation District
Location: Moccasin Point, California
Project Description:
This Project involves the initial emergency response, investigation,
and remediation of a significant gasoline subsurface discharge which
was impacting the reservoir waters. Gasoline leaked from several locations
along a pipeline from gravity feed underground storage tanks connected
to a floating marina. The reservoir water level was rising 1.0 feet
per day. AGS excavated a large quantity of contaminated soil ahead of
the advancing water level, installed numerous soil borings, and monitoring
wells. Approximately 90,000 gallons of contaminated ground water was
collected from surface springs and interceptor trenches, remediated
and disposed. The project area was submerged below approximately 50
feet of water. Monitoring wells were extended by AGS divers to facilitate
monitoring. Lake water contaminate and chemical parameter profiles,
bottom sediment sampling, and remediation of excavated soils are currently
in progress.
Submerged soil borings were conducted with a barge mounted drill rig.
Additional groun d
water studies were conducted to assess the contaminant plume remaining
in the fractured bedrock beneath the reservoir. AGS excavated and remediated
the remaining contaminated soil when the reservoir levels drop in the
fall of 1994. A Final Remediation Plan was prepared and a ground water
treatment system installed. AGS is currently conducting the long term
monitoring.
Estimated Completion Date: 1997
Contractor Status: Prime Contractor and Project Manager
Owner Contact: Mr. Blaine L. Cornell, Don Pedro Recreation Agency,
31 Bonds Flat Road, La Grange, California 95329, (209) 852-2396
|